Our Project

Rehabilitation and Upgradation to Four laning of Binjhabahal to Telebani Section, km. 414.000 to km. 491.710 (Design Chainage km. 414.982 to km. 493.300) of NH-6 (New NH-49) in the State of Odisha under NHDP-IV, on Hybrid Annuity Mode

Date of Signing of Concession Agreement: 16/01/2017

Bid Project Cost 1161.40 Cr
Appointed Date 15/01/2018
Construction Period 910 Days
Scheduled Date of Completion 13/07/2020
Actual Date of Completion 31/05/2022
O&M Period (Years) 15 Years

Utility Shifting Status

Electrical Completed
PHE Completed
Removal of Encroachment Completed
Tree Cutting Completed

Preconstruction Activity

Camp & Establishment Set up Completed
Casting Yard including gantries Completed
Batching Plant Set up with all equipment Completed

Land Acquisition Status

Total Land Required 425.821 Ha
Total Land Available 407.452 Ha
Additional Land Requirement 18.369 Ha
Likely availability of remaining land
Project works Status Completed

Major Bridge

Foundation Completed
Substructure Completed
Superstructure Completed

Minor Bridge

Foundation Completed
Substructure Completed
Superstructure Completed

ROB

Foundation Not Available
Substructure Not Available
Superstructure Not Available

Underpass

Foundation Not Available
Substructure Not Available
Superstructure Not Available

Box Culvert

Foundation Completed
Substructure Completed
Superstructure Completed
Foot over Bridge Not Available
SERVICE ROAD Completed
RCC DRAIN Completed
MAIN CARRIAGEWAY Completed
Total Physical Progress 100%