Our Project
Rehabilitation and Upgradation to Four laning of Binjhabahal to Telebani Section, km. 414.000 to km. 491.710 (Design Chainage km. 414.982 to km. 493.300) of NH-6 (New NH-49) in the State of Odisha under NHDP-IV, on Hybrid Annuity Mode
Date of Signing of Concession Agreement: 16/01/2017
| Bid Project Cost | 1161.40 Cr |
| Appointed Date | 15/01/2018 |
| Construction Period | 910 Days |
| Scheduled Date of Completion | 13/07/2020 |
| Actual Date of Completion | 31/05/2022 |
| O&M Period (Years) | 15 Years |
Utility Shifting Status
| Electrical | Completed |
| PHE | Completed |
| Removal of Encroachment | Completed |
| Tree Cutting | Completed |
Preconstruction Activity
| Camp & Establishment Set up | Completed |
| Casting Yard including gantries | Completed |
| Batching Plant Set up with all equipment | Completed |
Land Acquisition Status
| Total Land Required | 425.821 Ha |
| Total Land Available | 407.452 Ha |
| Additional Land Requirement | 18.369 Ha |
| Likely availability of remaining land | |
| Project works Status | Completed |
Major Bridge
| Foundation | Completed |
| Substructure | Completed |
| Superstructure | Completed |
Minor Bridge
| Foundation | Completed |
| Substructure | Completed |
| Superstructure | Completed |
ROB
| Foundation | Not Available |
| Substructure | Not Available |
| Superstructure | Not Available |
Underpass
| Foundation | Not Available |
| Substructure | Not Available |
| Superstructure | Not Available |
Box Culvert
| Foundation | Completed |
| Substructure | Completed |
| Superstructure | Completed |
| Foot over Bridge | Not Available |
| SERVICE ROAD | Completed |
| RCC DRAIN | Completed |
| MAIN CARRIAGEWAY | Completed |
| Total Physical Progress | 100% |